Multi Modal Terminal at V

165 0

The Rs 169.59 Crore Multi Modal Terminal (MMT) being built at Varanasi by Inland Waterways Authority of India under Jal Marg Vikas project is set to be completed by November this year. This would be a major landmark for the project.

The construction of the Rs 280. 90 Crore MMT at Sahibganj is to be completed by May, 2019, and the one at Haldia, being constructed at a cost of Rs 517.36 Crore, is scheduled to  be completed by December 2019. In addition to this the work on the Rs 359.20 Crore state-of-the-art navigational lock at Farakka is to  be completed By June, 2019.  Contract for maintenance dredging in the Farakka-Kahalgaon stretch of the river  was awarded in April, 2018, for Rs 150 Crore,  and work on this has started.

The work for construction of two Inter-Modal Terminals (IMT)on NW-1, at Ghazipur in Uttar Pradesh and Kalughat in Bihar will be awarded this year.